About the Link Community Hub Project
The Link Community Hub - opening Spring 2026!
After 3 years of planning and fundraising work has started on the transformation of the Link building into a wonderful new resource for Church and Community.
Please watch this space for pictures of the work as it progresses.
The Hub will provide attractive community spaces and purpose built consulting rooms for Citizens Advice and Crossways Counselling. It will be fully accessible with a lift to the 1st floor.
We are grateful to all our donors who together have contributed £2.25m – parishioners, the wider community and local councils.
Upstairs
A meeting room and 3 counselling rooms
A new home for Crossways Counselling and Citizens Advice
Downstairs
A large and attractive community room
Kitchen
Office
Fully accessible
Lift access to 1st floor
Accessible WC
A Hub for all the Community!
November Update
We are now halfway through the project with the roof watertight and the Link once again connected to St Bart’s Church. Work is now protected from the weather and before Christmas the scaffolding will come down and the first fix of electricals and plumbing will be progressing at pace.
The shape of the upper floor is becoming clear with the 3 consulting rooms starting to take shape. Downstairs the hall feels fantastic and is a great size.

|
 |
A counselling room will go beyond the slim pillar-
plenty of room height! |
The new covered walkway! |
|
|
|
 |
 |
|
Counselling room above the kitchen |
Plenty of Height! |
 |
 |
|
|
|
 |
 |
If you wish to read the planning statement and look at the proposed drawings you can find them at the link below:
If you have any questions about the Hub project, please talk to members of the Project team - Andrew Culshaw, Cathy Moore or Debbie Peet or contact them via the parish office at office@haslemereparish.org